Substation Scout

Rivanna Solar

PJM queue ID AC1-116 Terminal status

Queue IDAC1-116
Project nameRivanna Solar
Status (as published)Withdrawn
SubstationMount Eagle
Point of interconnectionMount Eagle 34.5kV
CountyAlbemarle
StateVA
Voltage34.5 kV
Capacity4.7 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-04-17
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy12.5
Mw Capacity4.7
Mfo12.5
Withdrawn Date6/5/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.