Substation Scout

Rockport-Duff-Coleman 345 kV

PJM queue ID AC1-040 Terminal status

Queue IDAC1-040
Project nameRockport-Duff-Coleman 345 kV
Status (as published)Withdrawn
SubstationRockport-Duff-Coleman
Point of interconnectionRockport-Duff-Coleman 345 kV
CountySpencer
StateIN
Voltage345 kV
Capacity57 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2020-12-31
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy150
Mw Capacity57
Mfo150
Withdrawn Date11/7/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.