Strykers Road Solar Farm

PJM queue ID AC1-018 Terminal status

Queue IDAC1-018
Project nameStrykers Road Solar Farm
Status (as published)Withdrawn
SubstationMorris Park
Point of interconnectionMorris Park 12.47kV
CountyWarren
StateNJ
Voltage12.5 kV
Capacity0.5 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2019-07-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1.4
Mw Capacity0.5
Mfo1.4
Withdrawn Date8/4/2020