Substation Scout

Tri-State Solar

PJM queue ID AC1-012 Terminal status

Queue IDAC1-012
Project nameTri-State Solar
Status (as published)Withdrawn
SubstationRupert
Point of interconnectionRupert 34.5kV
CountyGreenbrier
StateWV
Voltage34.5 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2017-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy5
Mw Capacity0
Mfo5
Withdrawn Date7/30/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.