Substation Scout

Zion-Stateline

PJM queue ID AC1-005 Terminal status

Queue IDAC1-005
Project nameZion-Stateline
Status (as published)Withdrawn
SubstationZion-Stateline
Point of interconnectionZion-Stateline
CountyCook
StateIL
VoltageNot reported
Capacity1,000 MW
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operation2021-12-31
Source datasetserial

Additional filed fields

Project TypeMerchant Transmission
Mfo1000
Withdrawn Date6/6/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.