Substation Scout

Wye Mills 25kV

PJM queue ID AB2-185 Terminal status

Queue IDAB2-185
Project nameWye Mills 25kV
Status (as published)Withdrawn
SubstationWye Mills
Point of interconnectionWye Mills 25kV
CountyQueen Anne's
StateMD
Voltage25 kV
Capacity5.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2017-06-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy8
Mw Capacity5.6
Mfo8
Withdrawn Date4/14/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.