Substation Scout

Massey 25kV

PJM queue ID AB2-183 Terminal status

Queue IDAB2-183
Project nameMassey 25kV
Status (as published)Withdrawn
SubstationMassey
Point of interconnectionMassey 25kV
CountyKent
StateMD
Voltage25 kV
Capacity14 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2017-06-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity14
Mfo20
Withdrawn Date5/20/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.