Substation Scout

138kV Bus 5 Beckjord Battery

PJM queue ID AB2-178 Terminal status

Queue IDAB2-178
Project name138kV Bus 5 Beckjord Battery
Status (as published)Withdrawn
SubstationBeckjord
Point of interconnectionBeckjord 138kV
CountyClermont
StateOH
Voltage138 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2018-11-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.8
Mw Capacity0
Mfo19.8
Withdrawn Date12/10/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.