Wattsville-Wallops Island 69kV

PJM queue ID AB2-164 Terminal status

Queue IDAB2-164
Project nameWattsville-Wallops Island 69kV
Status (as published)Withdrawn
SubstationWattsville-Wallops Island
Point of interconnectionWattsville-Wallops Island 69kV
CountyAccomack
StateVA
Voltage69 kV
Capacity7.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2018-01-01
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity7.6
Mfo20
Withdrawn Date9/26/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.