Substation Scout

Gilbert 34.5kV

PJM queue ID AB2-127 Terminal status

Queue IDAB2-127
Project nameGilbert 34.5kV
Status (as published)Withdrawn
SubstationGilbert
Point of interconnectionGilbert 34.5kV
CountyHunterdon
StateNJ
Voltage34.5 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2018-06-29
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy16
Mw Capacity0
Mfo16
Withdrawn Date12/2/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.