Substation Scout

Burlington 480V

PJM queue ID AB2-107 Terminal status

Queue IDAB2-107
Project nameBurlington 480V
Status (as published)Withdrawn
SubstationBurlington 480V
Point of interconnectionBurlington 480V
CountyBurlington
StateNJ
VoltageNot reported
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2016-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0.21
Mw Capacity0
Mfo0.21
Withdrawn Date9/30/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.