Substation Scout

Culpeper 34.5kV

PJM queue ID AB2-023 Terminal status

Queue IDAB2-023
Project nameCulpeper 34.5kV
Status (as published)Withdrawn
SubstationCulpeper
Point of interconnectionCulpeper 34.5kV
CountyCulpeper
StateVA
Voltage34.5 kV
Capacity9.7 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2017-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy15
Mw Capacity9.7
Mfo15
Withdrawn Date3/30/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.