Substation Scout

Hagerstown Solar Facility

PJM queue ID AB2-004 Terminal status

Queue IDAB2-004
Project nameHagerstown Solar Facility
Status (as published)Withdrawn
SubstationHalfway-Milnor
Point of interconnectionHalfway-Milnor 34.5kV
CountyWashington
StateMD
Voltage34.5 kV
Capacity2.1 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2018-03-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy5.4
Mw Capacity2.1
Mfo5.4
Withdrawn Date10/23/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.