Substation Scout

Franklin Generation Facility

PJM queue ID AB1-171 Terminal status

Queue IDAB1-171
Project nameFranklin Generation Facility
Status (as published)Withdrawn
SubstationFranklin
Point of interconnectionFranklin 25kV
CountyGreene
StatePA
Voltage25 kV
Capacity20 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2019-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity20
Mfo20
Withdrawn Date10/22/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.