Mason Energy Center
PJM queue ID AB1-169 Terminal status
| Queue ID | AB1-169 |
|---|---|
| Project name | Mason Energy Center |
| Status (as published) | Withdrawn |
| Substation | Stuart |
| Point of interconnection | Stuart 345kV |
| County | Mason |
| State | KY |
| Voltage | 345 kV |
| Capacity | 1,100 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2023-06-30 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 1150 |
| Mw Capacity | 1100 |
| Mfo | 1150 |
| Withdrawn Date | 2/9/2022 |