Substation Scout

South Cumberland 69kV

PJM queue ID AB1-167 Terminal status

Queue IDAB1-167
Project nameSouth Cumberland 69kV
Status (as published)Withdrawn
SubstationSouth Cumberland
Point of interconnectionSouth Cumberland 69kV
CountyNoble
StateOH
Voltage69 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2017-08-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity0
Mfo50
Withdrawn Date11/30/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.