Substation Scout

Wakefield 34.5kV

PJM queue ID AB1-155 Terminal status

Queue IDAB1-155
Project nameWakefield 34.5kV
Status (as published)Withdrawn
SubstationWakefield
Point of interconnectionWakefield 34.5kV
CountySurry
StateVA
Voltage34.5 kV
Capacity3.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2017-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity3.8
Mfo10
Withdrawn Date11/16/2015

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.