King of Prussia

PJM queue ID AB1-120 Terminal status

Queue IDAB1-120
Project nameKing of Prussia
Status (as published)Withdrawn
SubstationKing of Prussia
Point of interconnectionKing of Prussia
CountyMontgomery
StatePA
VoltageNot reported
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2016-03-14
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0.8
Mw Capacity0
Mfo0.8
Withdrawn Date4/22/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.