Graceton-Safe Harbor 230kV

PJM queue ID AB1-102 Terminal status

Queue IDAB1-102
Project nameGraceton-Safe Harbor 230kV
Status (as published)Withdrawn
SubstationGraceton-Safe Harbor
Point of interconnectionGraceton-Safe Harbor 230kV
CountyNot reported
StateNot reported
Voltage230 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operation2016-06-01
Source datasetserial

Additional filed fields

Project TypeMerchant Transmission
Withdrawn Date9/20/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.