Substation Scout

Sunnymeade Road 13kV

PJM queue ID AB1-099 Terminal status

Queue IDAB1-099
Project nameSunnymeade Road 13kV
Status (as published)Withdrawn
SubstationSunnymeade Road
Point of interconnectionSunnymeade Road 13kV
CountySomerset
StateNJ
Voltage13 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2016-09-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy2
Mw Capacity0
Mfo2
Withdrawn Date6/16/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.