Lime Kiln-Aqueduct 34.5kV

PJM queue ID AB1-066 Terminal status

Queue IDAB1-066
Project nameLime Kiln-Aqueduct 34.5kV
Status (as published)Withdrawn
SubstationLime Kiln-Aqueduct
Point of interconnectionLime Kiln-Aqueduct 34.5kV
CountyFrederick
StateMD
Voltage34.5 kV
Capacity7.5 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2016-12-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.8
Mw Capacity7.5
Mfo19.8
Withdrawn Date3/2/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.