Huron 69kV

PJM queue ID AB1-030 Terminal status

Queue IDAB1-030
Project nameHuron 69kV
Status (as published)Withdrawn
SubstationHuron
Point of interconnectionHuron 69kV
CountyAtlantic
StateNJ
Voltage69 kV
Capacity3.5 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2016-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy7.5
Mw Capacity3.5
Mfo23
Withdrawn Date6/28/2016