Substation Scout

Columbia 115kV

PJM queue ID AB1-022 Terminal status

Queue IDAB1-022
Project nameColumbia 115kV
Status (as published)Withdrawn
SubstationColumbia
Point of interconnectionColumbia 115kV
CountyLouisa
StateVA
Voltage115 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2017-03-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy2
Mw Capacity0
Mfo2
Withdrawn Date4/6/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.