Newlinville 230 kV

PJM queue ID AB1-019 Terminal status

Queue IDAB1-019
Project nameNewlinville 230 kV
Status (as published)Withdrawn
SubstationNewlinville
Point of interconnectionNewlinville 230 kV
CountyChester
StatePA
Voltage230 kV
Capacity100 MW
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operation2018-06-01
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeMerchant Transmission
Mfo100
Withdrawn Date4/12/2018