Substation Scout

Earleys-Northampton 230kV

PJM queue ID AA2-181 Terminal status

Queue IDAA2-181
Project nameEarleys-Northampton 230kV
Status (as published)Withdrawn
SubstationEarleys-Northampton
Point of interconnectionEarleys-Northampton 230kV
CountyNorthhampton
StateNC
Voltage230 kV
Capacity56 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2016-06-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy80
Mw Capacity56
Mfo80
Withdrawn Date5/22/2015

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.