Substation Scout

East Towanda 34.5kV

PJM queue ID AA2-135 Terminal status

Queue IDAA2-135
Project nameEast Towanda 34.5kV
Status (as published)Withdrawn
SubstationEast Towanda
Point of interconnectionEast Towanda 34.5kV
CountyBradford
StatePA
Voltage34.5 kV
Capacity19.9 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2017-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.9
Mw Capacity19.9
Mfo19.9
Withdrawn Date5/17/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.