Substation Scout

Niles Valley 34.5kV

PJM queue ID AA2-081 Terminal status

Queue IDAA2-081
Project nameNiles Valley 34.5kV
Status (as published)Withdrawn
SubstationNiles Valley
Point of interconnectionNiles Valley 34.5kV
CountyTioga
StatePA
Voltage34.5 kV
Capacity19.9 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2018-08-28
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.9
Mw Capacity19.9
Mfo19.9
Withdrawn Date3/15/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.