Ellsworth-Eppler Junction 25kV

PJM queue ID AA2-080 Terminal status

Queue IDAA2-080
Project nameEllsworth-Eppler Junction 25kV
Status (as published)Withdrawn
SubstationEllsworth-Eppler Junction
Point of interconnectionEllsworth-Eppler Junction 25kV
CountyWashington
StatePA
Voltage25 kV
Capacity19.9 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2017-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.9
Mw Capacity19.9
Mfo19.9
Withdrawn Date12/2/2015