Substation Scout

Kewanee 138 kV

PJM queue ID AA2-039 Terminal status

Queue IDAA2-039
Project nameKewanee 138 kV
Status (as published)Withdrawn
SubstationKewanee
Point of interconnectionKewanee 138 kV
CountyHenry
StateIL
Voltage138 kV
Capacity19.5 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2016-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy150
Mw Capacity19.5
Mfo150
Withdrawn Date4/16/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.