West Cambridge 12kV

PJM queue ID AA2-036 Terminal status

Queue IDAA2-036
Project nameWest Cambridge 12kV
Status (as published)Withdrawn
SubstationWest Cambridge
Point of interconnectionWest Cambridge 12kV
CountyDorchester
StateMD
Voltage12 kV
Capacity5.3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2015-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy14
Mw Capacity5.3
Mfo14
Withdrawn Date10/6/2015

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.