Substation Scout

St. Claire 13kV

PJM queue ID AA1-130 Terminal status

Queue IDAA1-130
Project nameSt. Claire 13kV
Status (as published)Withdrawn
SubstationSt. Claire
Point of interconnectionSt. Claire 13kV
CountyFranklin
StateOH
Voltage13 kV
Capacity3 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2015-11-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy5
Mw Capacity3
Mfo5
Withdrawn Date3/31/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.