Kings Creek-Pocomoke 138kV

PJM queue ID AA1-107 Terminal status

Queue IDAA1-107
Project nameKings Creek-Pocomoke 138kV
Status (as published)Withdrawn
SubstationKings Creek-Pocomoke
Point of interconnectionKings Creek-Pocomoke 138kV
CountySomerset
StateMD
Voltage138 kV
Capacity15.9 MW
Resource (as published)Biomass
Resource categoryOther (normalised for filtering)
Target commercial operation2016-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.9
Mw Capacity15.9
Mfo19.9
Withdrawn Date3/31/2015

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.