Substation Scout

Tait 69kV

PJM queue ID AA1-101 Terminal status

Queue IDAA1-101
Project nameTait 69kV
Status (as published)Withdrawn
SubstationTait
Point of interconnectionTait 69kV
CountyMontgomery
StateOH
Voltage69 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2018-05-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity0
Mfo20
Withdrawn Date12/13/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.