USAP-Woodville 138kV

PJM queue ID AA1-088 Terminal status

Queue IDAA1-088
Project nameUSAP-Woodville 138kV
Status (as published)Withdrawn
SubstationUSAP-Woodville
Point of interconnectionUSAP-Woodville 138kV
CountyAllegheny
StatePA
Voltage138 kV
Capacity100 MW
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operation2015-06-01
Source datasetserial

Additional filed fields

Project TypeMerchant Transmission
Mfo100
Withdrawn Date11/11/2015