Huron 23kV

PJM queue ID AA1-075 Terminal status

Queue IDAA1-075
Project nameHuron 23kV
Status (as published)Withdrawn
SubstationHuron
Point of interconnectionHuron 23kV
CountyAtlantic
StateNJ
Voltage23 kV
Capacity7.5 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2015-11-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy7.5
Mw Capacity7.5
Mfo7.5
Withdrawn Date5/29/2015