Substation Scout

McConnellsburg-Guilford 138kV

PJM queue ID AA1-045 Terminal status

Queue IDAA1-045
Project nameMcConnellsburg-Guilford 138kV
Status (as published)Withdrawn
SubstationMcConnellsburg-Guilford
Point of interconnectionMcConnellsburg-Guilford 138kV
CountyVenango
StatePA
Voltage138 kV
Capacity308 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2015-12-18
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy308
Mw Capacity308
Mfo308
Withdrawn Date11/3/2015

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.