Substation Scout

Perryman 230kV or 115kV

PJM queue ID A47 Terminal status

Queue IDA47
Project namePerryman 230kV or 115kV
Status (as published)Withdrawn
SubstationPerryman or
Point of interconnectionPerryman 230kV or 115kV
CountyHarford
StateMD
Voltage230 kV
Capacity740 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operationNot reported
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy740
Mw Capacity740
Mfo740
Withdrawn Date8/30/1999