Passyunk 230 kV

PJM queue ID A27 Terminal status

Queue IDA27
Project namePassyunk 230 kV
Status (as published)Withdrawn
SubstationPassyunk
Point of interconnectionPassyunk 230 kV
CountyPhiladelphia
StatePA
Voltage230 kV
Capacity515 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operationNot reported
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy615
Mw Capacity515
Mfo615
Withdrawn Date4/30/2002