Queue request Company JV was listed in the NV Energy interconnection queue at the end of 2025 as a 50 MW battery project in Carson City, NV, according to Berkeley Lab’s queue data file. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 30, 2023.
| Queue ID | Company JV |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Not reported |
| Point of interconnection | Not reported |
| County | Carson City |
| State | NV |
| Voltage | Not reported |
| Capacity | 50 MW |
| Resource (as published) | Battery |
| Resource category | Battery (normalized for filtering) |
| Proposed online date | 2023-09-30 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Carson City, NV: 3 requests in the NV Energy queue, 1 active totaling 50 MW.
Tracked changes
Not tracked. NV Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | NV Energy |
|---|---|
| Interconnection service | NRIS/ERIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Queue date | 2019-03-25 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.