Substation Scout

NV Energy request Company 204

NV Energy queue ID Company 204

Queue request Company 204 was listed in the NV Energy interconnection queue at the end of 2025 as a 100 MW battery project in Clark County, NV, according to Berkeley Lab’s queue data file. Its status as of December 31, 2025 was “Suspended”, with a proposed online date of November 30, 2024.

Queue IDCompany 204
Project nameNot reported
Status (as published)Suspended
SubstationNot reported
Point of interconnectionNot reported
CountyClark
StateNV
VoltageNot reported
Capacity100 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2024-11-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Clark, NV: 173 requests in the NV Energy queue, 79 active totaling 18,326.3 MW.

Tracked changes

Not tracked. NV Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNV Energy
Interconnection serviceNRIS
Project typeGeneration
Queue date2021-09-29

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first