Substation Scout

NV Energy request 25-00431

NV Energy queue ID 25-00431

Queue request 25-00431 was listed in the NV Energy interconnection queue at the end of 2025 as a 250 MW battery project in Storey County, NV, according to Berkeley Lab’s queue data file. Its status as of December 31, 2025 was “Active”, with a proposed online date of August 1, 2029.

Queue ID25-00431
Project nameNot reported
Status (as published)Active
SubstationNot reported
Point of interconnectionNot reported
CountyStorey
StateNV
VoltageNot reported
Capacity250 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2029-08-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Storey, NV: 15 requests in the NV Energy queue, 9 active totaling 3,410 MW.

Tracked changes

Not tracked. NV Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNV Energy
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Queue date2025-07-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first