Substation Scout

ONALASKA substation interconnection queue

1 active project totaling 150 MW in the MISO queue, plus 1 with terminal status (shown grayed).

2 MISO queue filings name ONALASKA as the point of interconnection, all in Trinity County, TX.

1active projects
150active MW
2total filed
Queue IDProjectkVMWResourceStatus
J3455 Not reported n/r 250 Solar Withdrawn
J4103 Not reported n/r 150 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.