Substation Scout

Minntac Substation substation interconnection queue

1 active project totaling 100 MW in the MISO queue, plus 2 with terminal status (shown grayed).

3 MISO queue filings name Minntac Substation as the point of interconnection, all in St. Louis County, MN.

1active projects
100active MW
3total filed
Queue IDProjectkVMWResourceStatus
G591 Not reported 230 700 Gas Withdrawn
G424 Not reported n/r 100 Wind Operational
G660 Not reported 115 50 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.