Hoot Lake substation interconnection queue

1 active project totaling 49.9 MW in the MISO queue, plus 1 with terminal status (shown grayed).

2 MISO queue filings name Hoot Lake as the point of interconnection, all in Otter Tail County, MN.

1active projects
49.9active MW
2total filed
Queue IDProjectkVMWResourceStatus
R1006 Replace 350 MW of ALTW.FPL_DAEC Unit with Solar; Duane Arnold 115 350 Hybrid Withdrawn
R1001 Replace Hoot Lake units 2 and 3 (144.8 MW) with Seventeen (17) Sungrow 3 MW solar inverters and PV panels at 49.9 MW; Hoot Lake 2 & 3 115 49.9 Hybrid Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.