Emery Substation substation interconnection queue

1 active project totaling 600 MW in the MISO queue, plus 1 with terminal status (shown grayed).

2 MISO queue filings name Emery Substation as the point of interconnection, all in Cerro Gordo County, IA.

1active projects
600active MW
2total filed
Queue IDProjectkVMWResourceStatus
G186 Not reported n/r 600 Gas Operational
J447 Not reported 161 150 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.