Substation Scout

Ellendale substation interconnection queue

1 active project totaling 300 MW in the MISO queue, plus 2 with terminal status (shown grayed).

3 MISO queue filings name Ellendale as the point of interconnection, all in ND.

1active projects
300active MW
3total filed
Queue IDProjectkVMWResourceStatus
J2327 Not reported 345 300 Wind Withdrawn
J3280 Not reported n/r 300 Wind Active
J1990 Not reported 345 250 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first