Substation Scout

Dodge Center Substation substation interconnection queue

2 active projects totaling 33 MW in the MISO queue.

2 MISO queue filings name Dodge Center Substation as the point of interconnection, all in Dodge County, MN.

2active projects
33active MW
2total filed
Queue IDProjectkVMWResourceStatus
G242 Not reported n/r 19 Wind Operational
G171 Not reported n/r 14 Wind Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.