BISON substation interconnection queue

3 active projects totaling 879 MW in the MISO queue.

3 MISO queue filings name BISON as the point of interconnection, all in Cass County, ND.

3active projects
879active MW
3total filed
Queue IDProjectkVMWResourceStatus
J3163 Not reported n/r 479 Other Active
J1588 Not reported n/r 200 Solar Active
S1079 Surplus; J1588 n/r 200 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.