Substation Scout

Bauer - Rapson substation interconnection queue

3 active projects totaling 415 MW in the MISO queue, plus 1 with terminal status (shown grayed).

4 MISO queue filings name Bauer - Rapson as the point of interconnection, all in MI.

3active projects
415active MW
4total filed
Queue IDProjectkVMWResourceStatus
J161 Not reported 345 155 Wind Operational
J075 Not reported 345 150 Wind Operational
J235 Not reported 345 110 Wind Operational
J185 Not reported 345 100 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first