AB Brown 345 - Reid EHV (BREC Terminal) substation interconnection queue

3 active projects totaling 800 MW in the MISO queue, plus 1 with terminal status (shown grayed).

4 MISO queue filings name AB Brown 345 - Reid EHV (BREC Terminal) as the point of interconnection, all in Henderson County, KY.

3active projects
800active MW
4total filed
Queue IDProjectkVMWResourceStatus
J2931 Not reported 345 400 Solar Active
J2844 Not reported 345 200 Battery Active
J2930 Not reported 345 200 Wind Active
J3779 Not reported 345 100 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.